Display Settings Command on the S1 // Projects Tab

Set time units and the currency symbol.

Duration Time Unit

Field Description
Hours Select this option to display all duration time fields in hours.
Days Select this option to display all duration time fields in days.

Work Time Unit

Field Description
Hours Select this option to display all work time fields in hours.
Days Select this option to display all work time fields in days.

Hours Per Time Period

Field Description
Use assigned calendar to specify the number of work hours for each time period Select this option to ignore the Hours/Days settings. Acumen will convert work and duration using the Hours per Time Period setting defined in each activities assigned calendar. Use the drop-down menu to select the default number of hours per day before selecting this option.

Elapsed Durations Time Unit

Field Description
Hours Select this option to display all work time fields in hours.
Days Select this option to display all work time fields in days.
Weeks Select this option to display all work time fields in weeks.

Culture

Field Description
Currency Symbol Enter the currently symbol that you want to use in the Activity view.